Table of contents
Table of Contents |
---|
"Bundle and execute" is a feature to instantiate for instantiating several checklists in parallel. This is possible by assigning a checklist template to several test objects and/or users at the same time. This results in several checklists that can be processed simultaneously. Depending on the activated option, there are the following possibilities:
Starting checklists with different test objects
Instantiation of checklists with different test objects (types) and different users
Instantiation of checklists with different test objects and assignment to different users
Instantiation of checklists with different test object types and the underlying test objects and assignment to different users
Instantiation of checklists with one test object and assignment to different users
For each selected test object and/or user, a separate checklist is started with the same checklist template. In the course of this, the created checklists open side by side and the execution of the checklists is possible.
The number of test objects is freely selectable. Any number of test objects can be selected for which a checklist with the corresponding checklist template is to be started simultaneously. Depending on the activated option, it is also possible to store several users. With the option "Assign multiple checklists" also check object types can be selected.Whether several users can be selected depends on the activated option (see below)A separate checklist with the same checklist template is started for each selected test object. The created checklists open next to each other and the checklists can be executed.
This feature is also available if checklist templates are restricted to test object types in the Template settings (Not possible at test object level).
Options:
When setting up this featurefunction, you can choose between three two options:
Starting checklists with different test objects
...
Instantiation of checklists with different test objects (types) and different users
Assign multiple Checklists: This allows assigning a checklist for several test objects to several persons. A due date and time can be selected. In addition to selecting individual test objects, test object types can also be selected. This creates a checklist for all underlying test objects. This enables the simultaneous instantiation of very many checklists at once. Attention should be paid to the following:
If more than 100 checklists are assigned, an additional confirmation dialog appears in which the number of checklists must be confirmed.
When all checklists have been assigned, a notification appears that everything worked.
If something failed, a notification appears that not all checklists could be assigned successfully
see Bulk Actions
Info |
---|
Key users can activate this feature through the Testify Customer Success Solution Team. For more information, visit Company settings. |
...
After assigning the checklists a success message appears and the view gets reset.
Info |
---|
For more information on executing checklists, see Execute checklist. Another type of multiple assignment is the feature Bulk Actions with extended options. |
Panel | ||||||
---|---|---|---|---|---|---|
| ||||||
This feature cannot be enabled if Offline mode is enabled. |